Case Study
In spite of the 2009 economy, Delta T Engineering did install a number of units at approximately half a dozen commercial office buildings within the NYC tri-state area. These customers experienced positive results and plan on expanding their Delta T Alert program with additional units in 2010.
Below are a few “Case Studies” of anomalies which the Delta T Alert monitoring system detected:
Case Study #1 – Condenser Water Pump Fused Disconnect
Case Study #2 – Circuit Breaker Panel – neutral wires
Case Study #3 – Dry Type Transformer
Delta T Engineering also tested the Delta T Alert system on Variable Frequency Drives (VFD’s)
Test Case #1 – VFD’s
Please be sure to check back with us, we will be adding “Case Studies” as they develop.
To learn more, click here or contact us at 877-321-0576
Below are a few “Case Studies” of anomalies which the Delta T Alert monitoring system detected:
Case Study #1 – Condenser Water Pump Fused Disconnect
Case Study #2 – Circuit Breaker Panel – neutral wires
Case Study #3 – Dry Type Transformer
Delta T Engineering also tested the Delta T Alert system on Variable Frequency Drives (VFD’s)
Test Case #1 – VFD’s
Please be sure to check back with us, we will be adding “Case Studies” as they develop.
To learn more, click here or contact us at 877-321-0576